πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

BATTERY STORAGE Β· MISO

Battery storage project J2549, Clark County

Battery storage project J2549, Clark County is a 75.0 MW battery storage request withdrawn in the MISO interconnection queue, in Clark County, Missouri, connecting to AMEREN MISSOURI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2549
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Sub T to Maywood 345kV line
Location
Clark County, Missouri
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
July 2027
Withdrawn
March 2023

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem