United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· MISO

Onshore wind project J2915, Clark County

Onshore wind project J2915, Clark County is a 223 MW onshore wind request withdrawn in the MISO interconnection queue, in Clark County, Missouri, connecting to AMEREN MISSOURI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2915
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Other_
Location
Clark County, Missouri
Technology
Wind: 223 MW
Total requested
223 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
July 2028
Withdrawn
October 2025

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.