United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· MISOSolar project J3085, Madison County
Solar project J3085, Madison County is a 75.0 MW solar request withdrawn in the MISO interconnection queue, in Madison County, Missouri, connecting to AMEREN MISSOURI.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3085
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- Fredericktown 138 kV Substation
- Location
- Madison County, Missouri
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- December 2025
- Withdrawn
- October 2025
Location
Marker shows the centre of Madison County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem