United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· MISO

Solar project J2680, Dunklin County

Solar project J2680, Dunklin County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Dunklin County, Missouri, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2680
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Jim Hill-Hayti South 161 kV Line
Location
Dunklin County, Missouri
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
October 2026
Withdrawn
March 2023

Location

Marker shows the centre of Dunklin County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Dunklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem