United States βΊ Grid βΊ Interconnection queues βΊ Missouri
SOLAR Β· SPPSolar project GEN-2022-053, Barton County
Solar project GEN-2022-053, Barton County is a 138 MW solar request withdrawn in the SPP interconnection queue, in Barton County, Missouri, connecting to NEET.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedMay 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-053
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NEET
- Connection point (POI)
- Wolf Creek-Blackberry 345 kV
- Location
- Barton County, Missouri
- Technology
- Solar: 138 MW
- Total requested
- 138 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- May 2023
Location
Marker shows the centre of Barton County; the queue data does not give exact sites.
Other requests in Barton County
- Solar + storage project GEN-2024-259, Barton CountySolar + storage Β· 200 MW Β· in study
- Onshore wind project GEN-2017-060, Barton CountyOnshore wind Β· 149 MW Β· built
- Onshore wind project GEN-2017-082, Barton CountyOnshore wind Β· 149 MW Β· built
- Onshore wind project GEN-2023-006, Barton CountyOnshore wind Β· 202 MW Β· withdrawn
- Solar project GEN-2021-026, Barton CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem