Solar project GEN-2022-084, Jasper County

Solar project GEN-2022-084, Jasper County is a 11.5 MW solar request withdrawn in the SPP interconnection queue, in Jasper County, Missouri, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-084
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Connection point (POI)
POI-Galena 69 kV interconnection substation through a 0.50 mile 69 kV gen-tie line
Location
Jasper County, Missouri
Technology
Solar: 11.5 MW
Total requested
11.5 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
18 October 2022
Proposed online date
July 2026
Withdrawn
June 2023

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.