United States โ€บ Grid โ€บ Interconnection queues โ€บ Massachusetts

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Massachusetts (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown538,420 MW
Active in queue768 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn538,420 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

53 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind
Offshore wind
1,309 MWWithdrawn / abandoned MAISO-NE Oct 2023target 2030
Offshore Wind
Offshore wind
882 MWWithdrawn / abandoned MAISO-NE Feb 2023target 2030
Battery Storage
Battery storage
529 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2023target 2028
Battery Storage
Battery storage
301 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2023target 2026
Battery Storage Increase (QP1238)
Battery storage
301 MWWithdrawn / abandoned Norfolk, MAISO-NE Feb 2023target 2027
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2023target 2026
Battery Storage
Battery storage
271 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2023target 2027
Battery Storage
Battery storage
262 MWWithdrawn / abandoned Worcester, MAISO-NE Jun 2023target 2024
Battery Storage
Battery storage
250 MWWithdrawn / abandoned Norfolk, MAISO-NE Sep 2023target 2027
Battery Storage
Battery storage
241 MWWithdrawn / abandoned Essex, MAISO-NE Mar 2023target 2027
Battery Storage
Battery storage
238 MWWithdrawn / abandoned Bristol, MAISO-NE Aug 2023target 2027
Battery Storage
Battery storage
202 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2023target 2028
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2023target 2026
Battery Storage
Battery storage
196 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2027
Battery Storage
Battery storage
190 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2023target 2027
Battery Storage
Battery storage
176 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2023target 2024
Battery Storage
Battery storage
172 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2027
Battery Storage
Battery storage
160 MWWithdrawn / abandoned Franklin, MAISO-NE Aug 2023target 2027
Battery Storage
Battery storage
152 MWWithdrawn / abandoned Hampden, MAISO-NE Jul 2023target 2026
Battery Storage
Battery storage
152 MWWithdrawn / abandoned Bristol, MAISO-NE Sep 2023target 2027
Battery Storage
Battery storage
152 MWWithdrawn / abandoned Hampden, MAISO-NE Sep 2023target 2027
Battery Storage
Battery storage
151 MWWithdrawn / abandoned Hampshire, MAISO-NE Sep 2023target 2027
Battery Storage
Battery storage
151 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2023target 2027
Battery Storage Increase (QP1362)
Battery storage
141 MWWithdrawn / abandoned Norfolk, MAISO-NE Mar 2023target 2027
Battery Storage
Battery storage
122 MWWithdrawn / abandoned Worcester, MAISO-NE Jul 2023target 2026
Battery Storage
Battery storage
115 MWWithdrawn / abandoned Norfolk, MAISO-NE Nov 2023target 2029
Battery Storage
Battery storage
109 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2023target 2027
Battery Storage
Battery storage
103 MWWithdrawn / abandoned Hampden, MAISO-NE Sep 2023target 2027
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Worcester, MAISO-NE May 2023target 2026
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Worcester, MAISO-NE May 2023target 2026
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Berkshire, MAISO-NE Apr 2023target 2026
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2023target 2027
Battery Storage
Battery storage
92.4 MWWithdrawn / abandoned Hampden, MAISO-NE May 2023target 2027
Battery Storage
Battery storage
76.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Dec 2023target 2027
Battery Storage
Battery storage
69.4 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2023target 2026
Battery Storage
Battery storage
50.0 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2023target 2028
Battery Storage
Battery storage
41.2 MWWithdrawn / abandoned Worcester, MAISO-NE Jul 2023target 2026
(Offshore wind Increase (Q700 +Q1154)
Offshore wind
38.8 MWWithdrawn / abandoned MAISO-NE Feb 2023target 2026
EE Group @ Blandford
Solar + storage
28.9 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2024
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Hampshire, MAISO-NE May 2023target 2027
NG DG @ Sykes Road
Battery storage
10.0 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2023target 2025
NG NEMA Group DER Study
Battery storage
10.0 MWWithdrawn / abandoned Essex, MAISO-NE Dec 2023target 2025
EE Group @ Doreen
Solar + storage
9.1 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2023target 2024
EE Valley DG Group Study
Solar
8.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Nov 2023target 2026
EE Group @ Southwick
Solar + storage
7.0 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2024
NG NEMA Group DER Study
Solar + storage
5.0 MWWithdrawn / abandoned Essex, MAISO-NE Dec 2023target 2025
Individual @ Montague
Battery storage
5.0 MWWithdrawn / abandoned Franklin, MAISO-NE Jun 2023target 2024
NG NEMA Group DER Study
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Dec 2023target 2025
Individual @ Piper
Other
4.1 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2026
Individual @ Partridge
Solar + storage
4.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2023target 2024
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)