BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 100 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1386
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid Berkshire - Plainfield 115 kV line Lat/Long: 42.49627608454711, -73.01015449707741
Location
Berkshire County, Massachusetts
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
26 April 2023
Proposed online date
December 2026
Withdrawn
October 2024

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.