OFFSHORE WIND Β· ISO-NE

Offshore wind

Offshore wind is a 1,309 MW offshore wind request withdrawn in the ISO-NE interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedJul 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1451
Grid region
ISO-NE (New England)
Connection point (POI)
Primary: Pottersville 115kV Substation, Secondary: Bridgewater 345kV Substation
Location
Massachusetts
Technology
Offshore Wind: 1,309 MW
Total requested
1,309 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
5 October 2023
Proposed online date
September 2030
Withdrawn
July 2024

Location

No county location in the queue data.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem