BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 109 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1419
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid 115KV Bates Street Substation
Location
Bristol County, Massachusetts
Technology
Battery: 109 MW
Total requested
109 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 June 2023
Proposed online date
April 2027
Withdrawn
March 2024

Location

Marker shows the centre of Bristol County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Bristol County