United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 262 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1415
Grid region
ISO-NE (New England)
Connection point (POI)
POI interconnection coordinates: 42.471953, -71.734165 Interconnecting to National Grid 345kV line (line ID: 343) via line tap (approx. 8.5 mi from Wachusett Substation and 14.9 mi from Sandy Pond Sub
Location
Worcester County, Massachusetts
Technology
Battery: 262 MW
Total requested
262 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
20 June 2023
Proposed online date
August 2024
Withdrawn
September 2024

Location

Marker shows the centre of Worcester County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Worcester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem