BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 115 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Norfolk County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2023 (completed)
  2. Withdrawn / abandonedFeb 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1462
Grid region
ISO-NE (New England)
Connection point (POI)
Tap on Belmont 115 kV - Stoughton Tap 115 kV Line with three breaker ring bus scheme. POI is located at the 1.75 miles from Stoughton 115kV substation and the 2.8 miles from Belmont Substation. Latitu
Location
Norfolk County, Massachusetts
Technology
Battery: 115 MW
Total requested
115 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
27 November 2023
Proposed online date
December 2029
Withdrawn
February 2024

Location

Marker shows the centre of Norfolk County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Norfolk County