🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 92.4 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1399
Grid region
ISO-NE (New England)
Connection point (POI)
The proposed POI is Buck Pond 115 kV substation, share gen leadline with QP1117.
Location
Hampden County, Massachusetts
Technology
Battery: 92.4 MW
Total requested
92.4 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
18 May 2023
Proposed online date
May 2027
Withdrawn
October 2025

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem