United States โ€บ Grid โ€บ Interconnection queues โ€บ Massachusetts

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Massachusetts (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown486,226 MW
Active in queue2,980 MW8 requests
Agreement signed2,475 MW6 requests
Withdrawn486,226 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

48 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind
Offshore wind
1,320 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2027
Offshore wind
Offshore wind
1,200 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2033
Offshore wind
Offshore wind
440 MWWithdrawn / abandoned MAISO-NE Aug 2021target 2026
Offshore wind Increase (QP909)
Offshore wind
386 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2027
Increase to Pumping load
Battery storage
333 MWWithdrawn / abandoned Berkshire, MAISO-NE Nov 2021target 2021
Battery Storage
Battery storage
276 MWWithdrawn / abandoned Suffolk, MAISO-NE Aug 2021target 2023
Storage
Battery storage
242 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2021target 2028
Streamfield
Battery storage
202 MWWithdrawn / abandoned Hampden, MAISO-NE Apr 2021target 2027
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Barnstable, MAISO-NE Dec 2021target 2024
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Berkshire, MAISO-NE Dec 2021target 2024
Battery Storage
Battery storage
189 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2021target 2027
Battery Storage
Battery storage
189 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2021target 2027
Battery Storage
Battery storage
150 MWWithdrawn / abandoned Bristol, MAISO-NE Dec 2021target 2027
Battery Storage
Battery storage
108 MWWithdrawn / abandoned Hampden, MAISO-NE Apr 2021target 2025
Battery Storage
Battery storage
105 MWWithdrawn / abandoned Franklin, MAISO-NE Mar 2021target 2029
Battery Storage
Battery storage
105 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2021target 2025
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Franklin, MAISO-NE Oct 2021target 2023
Energy Storage
Battery storage
99.9 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2021target 2024
Battery Storage
Battery storage
55.0 MWWithdrawn / abandoned Franklin, MAISO-NE Mar 2021target 2025
E. Winchendon Substation - NG WMA Group 3
Solar + storage
35.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Wendall Depot Substation - NG WMA Group 3
Solar + storage
28.0 MWWithdrawn / abandoned Franklin, MAISO-NE Oct 2021target 2027
Snow St. Substation - NG WMA Group 3
Solar + storage
27.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Stafford St. Substation - NG WMA Group 3
Solar + storage
22.4 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
N. Oxford Substation - NG WMA Group 3
Solar + storage
20.4 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Mar 2021target 2026
W. Charlton Substation - NG WMA Group 3
Battery storage
20.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Pratts Junc. Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Lashaway Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Meadow Street 552 Substation - NG WMA Group 3
Solar + storage
13.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Barre Substation - NG WMA Group 3
Solar + storage
12.4 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Millbury Substation - NG WMA Group 3
Solar + storage
11.7 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Ware Substation - NG WMA Group 3
Solar + storage
11.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Oct 2021target 2027
Treasure Valley Substation - NG WMA Group 3
Battery storage
10.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Solar + Battery Storage
Solar + storage
10.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Aug 2021target 2022
Crystal Lake Substation - NG WMA Group 3
Battery storage
8.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Little Rest Rd Substation - NG WMA Group 3
Solar + storage
5.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Royalston Substation - NG WMA Group 3
Solar + storage
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
E. Westminster Substation - NG WMA Group 3
Solar + storage
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Solar + Battery Storage
Solar + storage
4.9 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2021target 2021
Solar + Battery Storage
Solar + storage
4.5 MWWithdrawn / abandoned Berkshire, MAISO-NE Apr 2021target 2022
Solar plus Battery
Solar + storage
4.5 MWWithdrawn / abandoned Berkshire, MAISO-NE Aug 2021target 2022
Solar + Battery Storage
Solar + storage
4.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2021target 2022
Solar plus Battery
Solar + storage
3.6 MWWithdrawn / abandoned Berkshire, MAISO-NE Sep 2021target 2022
Solar + Battery Storage
Solar + storage
3.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Apr 2021target 2021
Solar + Battery Storage
Solar + storage
2.5 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2021target 2021
Solar + Battery Storage
Solar + storage
2.0 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2021target 2022
Solar
Solar + storage
1.0 MWWithdrawn / abandoned Dukes, MAISO-NE Jun 2021target 2022
Solar + Battery Storage
Solar + storage
1.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)