United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 200 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1206
Grid region
ISO-NE (New England)
Connection point (POI)
MA_NGRID Adams 115kV substation Bus ID: 113005
Location
Berkshire County, Massachusetts
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
30 December 2021
Proposed online date
December 2024
Withdrawn
March 2022

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Berkshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem