Solar

Solar is a 1.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Dukes County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1144
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 23 kV Line 4-99-99
Location
Dukes County, Massachusetts
Technology
Solar: 1.0 MW Β· Battery
Total requested
1.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
17 June 2021
Proposed online date
November 2022
Withdrawn
October 2021

Location

Marker shows the centre of Dukes County; the queue data does not give exact sites.