Solar project IC-1147, Monroe County Solar |
500 MW | Paused / redesign |
Monroe, GA | Southeast |
Jun 2023 | target 2030 |
Battery storage project IC-1170, Douglas County Battery storage |
500 MW | Paused / redesign |
Douglas, GA | Southeast |
Aug 2023 | target 2030 |
Gas project IC-1166, Coweta County Gas |
411 MW | Agreement signed |
Coweta, GA | Southeast |
Aug 2023 | target 2025 |
Gas project IC-1168, Coweta County Gas |
411 MW | Agreement signed |
Coweta, GA | Southeast |
Aug 2023 | target 2025 |
Gas project IC-1167, Coweta County Gas |
411 MW | Agreement signed |
Coweta, GA | Southeast |
Aug 2023 | target 2025 |
Battery storage project IC-1144, Bartow County Battery storage |
260 MW | Paused / redesign |
Bartow, GA | Southeast |
Jun 2023 | target 2028 |
Battery storage project IC-1223, Hall County Battery storage |
250 MW | Agreement signed |
Hall, GA | Southeast |
Dec 2023 | target 2028 |
Battery storage project IC-1222, Bartow County Battery storage |
250 MW | Agreement signed |
Bartow, GA | Southeast |
Dec 2023 | target 2027 |
Solar project IC-1149, Mitchell County Solar |
250 MW | Paused / redesign |
Mitchell, GA | Southeast |
Jul 2023 | target 2028 |
Solar project IC-1206, Laurens County Solar |
225 MW | Agreement signed |
Laurens, GA | Southeast |
Nov 2023 | target 2028 |
Hammond Solar Solar |
225 MW | In study |
Floyd, GA | Southeast |
Sep 2023 | target 2025 |
Battery storage project IC-1187, Wilkinson County Battery storage |
220 MW | Agreement signed |
Wilkinson, GA | Southeast |
Oct 2023 | target 2027 |
Pecan Energy Storage Solar + storage |
208 MW | In study |
Mitchell, GA | Southeast |
Oct 2023 | target 2029 |
Solar project IC-1195, Warren County Solar |
200 MW | Agreement signed |
Warren, GA | Southeast |
Oct 2023 | target 2028 |
Solar project IC-1204, Jefferson County Solar |
200 MW | Agreement signed |
Jefferson, GA | Southeast |
Nov 2023 | target 2028 |
Live Oak Solar Solar + storage |
200 MW | In study |
Laurens, GA | Southeast |
May 2023 | target 2026 |
Pepper Hammock 200 MW Solar |
200 MW | In study |
Glynn, GA | Southeast |
Aug 2023 | target 2026 |
Solar project IC-1152, Washington County Solar |
200 MW | Agreement signed |
Washington, GA | Southeast |
Jul 2023 | target 2027 |
Beaver Creek Solar Solar + storage |
183 MW | In study |
Baldwin, GA | Southeast |
Sep 2023 | target 2027 |
Solar project IC-1142, Baldwin County Solar |
183 MW | Agreement signed |
Baldwin, GA | Southeast |
May 2023 | target 2028 |
Red Dirt Solar Solar + storage |
153 MW | In study |
Talbot, GA | Southeast |
Apr 2023 | target 2026 |
Solar project IC-1165, Elbert County Solar |
150 MW | Paused / redesign |
Elbert, GA | Southeast |
Aug 2023 | target 2027 |
Solar project IC-1153, Wilcox County Solar |
150 MW | Paused / redesign |
Wilcox, GA | Southeast |
Jul 2023 | target 2027 |
Solar project IC-1172, Jefferson County Solar |
128 MW | Agreement signed |
Jefferson, GA | Southeast |
Sep 2023 | target 2028 |
TOCE GA 1 Solar Solar |
125 MW | In study |
Burke, GA | Southeast |
Aug 2023 | target 2026 |
Pelham Solar Solar |
120 MW | In study |
Charlton, GA | Southeast |
Sep 2023 | target 2025 |
SR Bacon II Solar Solar |
115 MW | In study |
Bacon, GA | Southeast |
Sep 2023 | target 2027 |
SR Norwood Solar Solar |
107 MW | Under construction |
Warren, GA | Southeast |
May 2023 | target 2026 |
Solar project IC-1136, Lincoln County Solar |
105 MW | Paused / redesign |
Lincoln, GA | Southeast |
Apr 2023 | target 2027 |
Battery storage project IC-1116, Carroll County Battery storage |
100 MW | Agreement signed |
Carroll, GA | Southeast |
Jan 2023 | target 2027 |
SR Bacon III Solar Solar |
100 MW | In study |
Bacon, GA | Southeast |
Sep 2023 | target 2028 |
SR Rochelle II Solar Solar |
90.0 MW | Under construction |
Wilcox, GA | Southeast |
Sep 2023 | target 2026 |
Solar project IC-1176, Glascock County Solar |
68.5 MW | Paused / redesign |
Glascock, GA | Southeast |
Sep 2023 | target 2028 |
SR Mendes Solar |
60.0 MW | Under construction |
Tattnall, GA | Southeast |
Jul 2023 | target 2026 |
Solar + storage project IC-1199, Lowndes County Solar + storage |
3.5 MW | Agreement signed |
Lowndes, GA | Southeast |
Nov 2023 | target 2025 |