SR Bacon III Solar

SR Bacon III Solar is a 100 MW solar request in interconnection study in the Southeast interconnection queue, in Bacon County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-186
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Offerman - Douglas 230 kV TL
Location
Bacon County, Georgia
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
Application Review in Progress
Queue status
Active
Entered queue
28 September 2023
Proposed online date
November 2028

Location

Marker shows the centre of Bacon County; the queue data does not give exact sites.