🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

SR Rochelle II Solar

SR Rochelle II Solar is a 90.0 MW solar request under construction in the Southeast interconnection queue, in Wilcox County, Georgia, connecting to Georgia Transmission.

Queue statusUnder construction
  1. PlanningQueued Sep 2023 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-183
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Fitzgerald - Pitts 115 kV TL
Location
Wilcox County, Georgia
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Study phase
Full NTP
Queue status
Active
Entered queue
20 September 2023
Proposed online date
November 2026

Location

Marker shows the centre of Wilcox County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Wilcox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem