SOLAR · SOUTHEASTSR Rochelle II Solar
SR Rochelle II Solar is a 90.0 MW solar request under construction in the Southeast interconnection queue, in Wilcox County, Georgia, connecting to Georgia Transmission.
Queue statusUnder construction
- PlanningQueued Sep 2023 (completed)
- Consented (completed)
- Construction (current stage)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-183
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- Fitzgerald - Pitts 115 kV TL
- Location
- Wilcox County, Georgia
- Technology
- Solar: 90.0 MW
- Total requested
- 90.0 MW
- Study phase
- Full NTP
- Queue status
- Active
- Entered queue
- 20 September 2023
- Proposed online date
- November 2026
Location
Marker shows the centre of Wilcox County; the queue data does not give exact sites.
Other requests in Wilcox County