United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Southeast (non-ISO utilities) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown449,966 MW
Active in queue12.7 GW63 requests
Agreement signed1,908 MW12 requests
Withdrawn12316.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 489, Roane County
Gas
1,689 MWIn study Roane, TNSoutheast Dec 2021target 2026
Gas project 483, Stewart County
Gas
1,600 MWIn study Stewart, TNSoutheast Oct 2021target 2025
Solar + storage project IC-942, Glynn County
Solar + storage
1,200 MWPaused / redesign Glynn, GASoutheast Mar 2021target 2025
Battery storage project IC-974, Fulton County
Battery storage
600 MWPaused / redesign Fulton, GASoutheast Jul 2021target 2025
Solar + storage project LGE-GIS-2021-008, Clark County
Solar + storage
500 MWPaused / redesign Clark, INSoutheast Mar 2021target 2026
Solar project IC-986, Lamar County
Solar
250 MWPaused / redesign Lamar, MSSoutheast Oct 2021target 2025
Solar project IC-972, Jasper County
Solar
250 MWPaused / redesign Jasper, GASoutheast Jul 2021target 2024
Solar project IC-990, Toombs County
Solar
200 MWPaused / redesign Toombs, GASoutheast Oct 2021target 2025
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
Solar + storage project LGE-GIS-2021-009, Hardin County
Solar + storage
200 MWPaused / redesign Hardin, KYSoutheast Mar 2021target 2026
Solar project IC-989, Johnson County
Solar
150 MWPaused / redesign Johnson, GASoutheast Oct 2021target 2025
Talbot Solar
Solar
150 MWIn study Talbot, GASoutheast Dec 20212023
Crossroads Solar
Solar + storage
150 MWIn study Liberty, GASoutheast Jun 2021target 2024
Solar + storage project IC-964, Emanuel County
Solar + storage
150 MWPaused / redesign Emanuel, GASoutheast Jun 2021target 2025
Dellwood Solar
Solar + storage
150 MWIn study Emanuel, GASoutheast May 20212023
Cherry Tree Solar
Solar + storage
150 MWIn study Washington, GASoutheast Dec 2021target 2025
Solar + storage project IC-1006, Liberty County
Solar + storage
150 MWPaused / redesign Liberty, GASoutheast Dec 2021target 2026
Solar project IC-988, Oglethorpe County
Solar
120 MWPaused / redesign Oglethorpe, GASoutheast Oct 2021target 2025
Solar project LGE-GIS-2021-007, Mccracken County
Solar
120 MWPaused / redesign Mccracken, KYSoutheast Mar 2021target 2026
Solar + storage project LGE-GIS-2021-018, Bath County
Solar + storage
110 MWPaused / redesign Bath, KYSoutheast May 2021target 2027
Solar + storage project LGE-GIS-2021-017, Mason County
Solar + storage
100 MWPaused / redesign Mason, KYSoutheast Apr 2021target 2026
Solar project LGE-GIS-2021-019, Boyle County
Solar
100 MWPaused / redesign Boyle, KYSoutheast May 2021target 2027
Solar project IC-1005, Burke County
Solar
100 MWPaused / redesign Burke, GASoutheast Dec 2021target 2026
Solar + storage project IC-980, Oglethorpe County
Solar + storage
100 MWPaused / redesign Oglethorpe, GASoutheast Aug 2021target 2024
Long Cane Solar
Solar + storage
80.0 MWIn study Troup, GASoutheast Jul 2021target 2024
Solar + storage project IC-999, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-971, Lowndes County
Solar + storage
80.0 MWPaused / redesign Lowndes, ALSoutheast Jul 2021target 2026
Solar + storage project IC-954, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Apr 2021target 2026
Solar + storage project IC-997, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-1000, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-979, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Aug 2021target 2026
Solar project IC-1001, Early County
Solar
80.0 MWPaused / redesign Early, GASoutheast Dec 2021target 2025
Solar project IC-943, Talladega County
Solar
80.0 MWPaused / redesign Talladega, ALSoutheast Mar 2021target 2025
Solar project IC-975, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Jul 2021target 2025
Solar project IC-1002, Decatur County
Solar
78.0 MWPaused / redesign Decatur, GASoutheast Dec 2021target 2025
Solar project 167, Darlington County
Solar
75.0 MWPaused / redesign Darlington, SCSoutheast Oct 2021target 2025
Solar + storage project JEA-Q009, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast Jul 2021target 2026
Solar project 293, Alachua County
Solar Β· Pleasant Solar, LLC
74.9 MWPaused / redesign Alachua, FLSoutheast Aug 2021target 2024
Solar project 424D, Madison County
Solar Β· FPL
74.5 MWIn study Madison, FLSoutheast Aug 2021target 2027
Solar project 424A, Leon County
Solar Β· FPL
74.5 MWIn study Leon, FLSoutheast Aug 2021target 2033
Solar project 424B, Leon County
Solar Β· FPL
74.5 MWIn study Leon, FLSoutheast Aug 2021target 2033
Solar project 424, Manatee County
Solar Β· FPL
74.5 MWIn study Manatee, FLSoutheast May 2021target 2027
Solar + storage project IC-955, Lowndes County
Solar + storage
58.0 MWPaused / redesign Lowndes, ALSoutheast Apr 2021target 2026
Hydro project 476, Lyon County
Hydro
18.0 MWIn study Lyon, KYSoutheast Apr 2021target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)