United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in SPP (Southwest Power Pool) (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26871.3 GW
Active in queue71.3 GW268 requests
Agreement signed0.0 MW0 requests
Withdrawn9926.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

268 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-340, Creek County
Gas
1,400 MWIn study Creek, OKSPP Mar 2025target 2032
Gas project GEN-2024-377, Harrison County
Gas
1,350 MWIn study Harrison, TXSPP Mar 2025target 2031
Gas project GEN-2024-379, Bossier Parish County
Gas
1,350 MWIn study Bossier Parish, LASPP Mar 2025target 2031
Gas project GEN-2024-132, Johnston County
Gas
1,300 MWIn study Johnston, OKSPP Mar 2025target 2031
Gas project GEN-2024-341, Pittsburg County
Gas
1,045 MWIn study Pittsburg, OKSPP Mar 2025target 2031
Gas project GEN-2024-129, Labette County
Gas
910 MWIn study Labette, KSSPP Mar 2025target 2030
Gas project GEN-2024-207, Jackson County
Gas
779 MWIn study Jackson, MOSPP Mar 2025target 2029
Gas project ERAS-2025-004, Oklahoma County
Gas
763 MWIn study Oklahoma, OKSPP Sep 2025target 2030
Gas project ERAS-2025-012, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Gas project ERAS-2025-011, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Gas project ERAS-2025-026, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-299, Oklahoma County
Gas
744 MWIn study Oklahoma, OKSPP Mar 2025target 2032
Gas project ERAS-2025-024, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-249, Pottawatomie County
Gas
721 MWIn study Pottawatomie, KSSPP Mar 2025target 2032
Gas project ERAS-2025-008, Sumner County
Gas
721 MWIn study Sumner, KSSPP Sep 2025target 2029
Gas project ERAS-2025-006, Reno County
Gas
718 MWIn study Reno, KSSPP Sep 2025target 2030
Gas project GEN-2024-128, Caddo County
Gas
690 MWIn study Caddo, OKSPP Mar 2025target 2030
Onshore wind project GEN-2024-345, Nowata County
Onshore wind
600 MWIn study Nowata, OKSPP Mar 2025target 2030
Gas project ERAS-2025-017, Finney County
Gas
600 MWIn study Finney, KSSPP Sep 2025target 2029
Gas project ERAS-2025-023, Rogers County
Gas
510 MWIn study Rogers, OKSPP Oct 2025target 2029
Solar + storage project GEN-2024-303, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-266, Potter County
Solar + storage
500 MWIn study Potter, TXSPP Mar 2025target 2033
Solar + storage project GEN-2024-165, Coal County
Solar + storage
500 MWIn study Coal, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-294, Mayes County
Solar + storage
500 MWIn study Mayes, OKSPP Mar 2025target 2030
Onshore wind project ERAS-2025-021, Hale County
Onshore wind
500 MWIn study Hale, TXSPP Oct 2025target 2030
Solar + storage project GEN-2024-304, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Gas project ERAS-2025-010, Oklahoma County
Gas
496 MWIn study Oklahoma, OKSPP Sep 2025target 2029
Gas project GEN-2024-321, Seminole County
Gas
493 MWIn study Seminole, OKSPP Mar 2025target 2030
Gas project GEN-2024-343, Harrison County
Gas
471 MWIn study Harrison, TXSPP Mar 2025target 2030
Gas project GEN-2024-247, Payne County
Gas
457 MWIn study Payne, OKSPP Mar 2025target 2030
Gas project ERAS-2025-007, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Oct 2025target 2030
Gas project ERAS-2025-013, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Sep 2025target 2030
Coal project ERAS-2025-009, Chouteau County
Coal
450 MWIn study Chouteau, OKSPP Oct 2025target 2026
Onshore wind project GEN-2024-141, Mercer County
Onshore wind
424 MWIn study Mercer, NDSPP Mar 2025target 2031
Solar + storage project GEN-2024-124, Lea County
Solar + storage
420 MWIn study Lea, NMSPP Mar 2025target 2028
Other project GEN-2025-SR9, Muskogee County
Other
410 MWIn study Muskogee, OKSPP May 2025target 2029
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2024-109, Bailey County
Onshore wind
401 MWIn study Bailey, TXSPP Mar 2025target 2031
Solar project GEN-2024-125, Elk County
Solar
400 MWIn study Elk, KSSPP Mar 2025target 2028
Solar project GEN-2024-136, Scott County
Solar
400 MWIn study Scott, KSSPP Mar 2025target 2029
Battery storage project GEN-2025-SR1, Henry County
Battery storage
400 MWIn study Henry, MOSPP Apr 2025target 2027
Solar + storage project ERAS-2025-020, Lea County
Solar + storage
400 MWIn study Lea, NMSPP Oct 2025target 2030
Onshore wind project GEN-2024-221, Roosevelt County
Onshore wind
400 MWIn study Roosevelt, NMSPP Mar 2025target 2030
Solar + storage project ERAS-2025-015, Finney County
Solar + storage
400 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GEN-2024-268, Muskogee County
Solar
390 MWIn study Muskogee, OKSPP Mar 2025target 2030
Solar project ERAS-2025-028, Hockley County
Solar
384 MWIn study Hockley, TXSPP Oct 2025target 2030
Gas project GEN-2024-213, Cass County
Gas
360 MWIn study Cass, NESPP Mar 2025target 2035
Gas project GEN-2024-323, Choctaw County
Gas
357 MWIn study Choctaw, OKSPP Mar 2025target 2029
Solar + storage project ERAS-2025-030, Chaves County
Solar + storage
350 MWIn study Chaves, NMSPP Oct 2025target 2030
Solar project GEN-2024-289, Henry County
Solar
350 MWIn study Henry, MOSPP Mar 2025target 2029
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)