Interconnection queue in SPP (Southwest Power Pool) (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8118.0 GW
Active in queue18.0 GW81 requests
Agreement signed1,671 MW8 requests
Withdrawn297,503 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

81 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-082, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2030
Gas project GEN-2024-081, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2029
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Solar + storage project GEN-2024-073, Lea County
Solar + storage
500 MWIn study Lea, NMSPP Oct 2024target 2028
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Gas project GEN-2024-020, Lancaster County
Gas
390 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-022, Gage County
Gas
390 MWIn study Gage, NESPP Oct 2024target 2030
Solar project GEN-2024-067, Cloud County
Solar
380 MWIn study Cloud, KSSPP Oct 2024target 2029
Solar project GEN-2024-046, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Solar project GEN-2024-045, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Solar project GEN-2024-025, Bowie County
Solar
300 MWIn study Bowie, TXSPP Oct 2024target 2030
Onshore wind project GEN-2025-GR1, Grant County
Onshore wind
300 MWIn study Grant, OKSPP Dec 2024target 2027
Solar project GEN-2024-078, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2024-038, Nemaha County
Solar
300 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar + storage project GEN-2024-050, Castro County
Solar + storage
300 MWIn study Castro, TXSPP Oct 2024target 2028
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Solar project GEN-2024-077, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2024-068, Morris County
Solar
300 MWIn study Morris, TXSPP Oct 2024target 2028
Onshore wind project GEN-2024-GR6, Kay County
Onshore wind
300 MWIn study Kay, OKSPP Jul 2024target 2027
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Solar + storage project GEN-2024-035, Brown County
Solar + storage
270 MWIn study Brown, SDSPP Oct 2024target 2027
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Solar project GEN-2024-063, Lamb County
Solar
256 MWIn study Lamb, TXSPP Oct 2024target 2027
Solar project GEN-2024-079, Curry County
Solar
250 MWIn study Curry, NMSPP Oct 2024target 2029
Solar project GEN-2024-083, Choctaw County
Solar
250 MWIn study Choctaw, OKSPP Oct 2024target 2029
Onshore wind project GEN-2024-042, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2028
Solar project GEN-2024-080, Curry County
Solar
250 MWIn study Curry, NMSPP Oct 2024target 2029
Onshore wind project GEN-2024-043, Roosevelt County
Onshore wind
250 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Onshore wind project GEN-2024-041, Floyd County
Onshore wind
250 MWIn study Floyd, TXSPP Oct 2024target 2029
Solar project GEN-2024-039, Nemaha County
Solar
250 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar project GEN-2024-032, Stevens County
Solar
250 MWIn study Stevens, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-062, Kingfisher County
Battery storage
230 MWIn study Kingfisher, OKSPP Oct 2024target 2028
Solar + storage project GEN-2024-069, Crawford County
Solar + storage
228 MWIn study Crawford, KSSPP Oct 2024target 2028
Onshore wind project GEN-2024-058, Nowata County
Onshore wind
200 MWIn study Nowata, OKSPP Oct 2024target 2028
Battery storage project GEN-2024-SR11, Garfield County
Battery storage
200 MWAgreement signed Garfield, OKSPP May 20242025
Solar project GEN-2024-SR7, Beaver County
Solar
200 MWIn study Beaver, OKSPP Jan 2024target 2027
Battery storage project GEN-2024-061, Cowley County
Battery storage
200 MWIn study Cowley, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-074, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Oct 2024target 2028
Battery storage project GEN-2024-SR6, Johnston County
Battery storage
200 MWIn study Johnston, OKSPP Feb 2024
Battery storage project GEN-2024-092, Roosevelt County
Battery storage
200 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Solar project GEN-2024-GR3, Lea County
Solar
196 MWIn study Lea, NMSPP Jun 2024target 2027
Onshore wind project GEN-2024-089, Curry County
Onshore wind
195 MWIn study Curry, NMSPP Oct 2024target 2029
Battery storage project GEN-2024-SR5, Creek County
Battery storage
177 MWAgreement signed Creek, OKSPP Feb 2024target 2026
Solar project GEN-2024-055, Vernon County
Solar
175 MWIn study Vernon, MOSPP Oct 2024target 2029
Battery storage project GEN-2024-034, Sargent County
Battery storage
175 MWIn study Sargent, NDSPP Oct 2024target 2029
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)