United States › Grid › Interconnection queues › New Mexico
SOLAR · SPPSolar project GEN-2024-080, Curry County
Solar project GEN-2024-080, Curry County is a 250 MW solar request in interconnection study in the SPP interconnection queue, in Curry County, New Mexico, connecting to SPS.
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-080
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- San Juan 230 kV Substation
- Location
- Curry County, New Mexico
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 30 October 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Curry County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Curry County
- Solar project GEN-2024-079, Curry CountySolar · 250 MW · in study
- Onshore wind project GEN-2024-089, Curry CountyOnshore wind · 195 MW · in study
- Gas project GEN-2001-005, Curry CountyGas · 640 MW · withdrawn
- Solar + storage project IA-PNM-2022-08, Curry CountySolar + storage · 500 MW · withdrawn
- Gas project GEN-2001-004, Curry CountyGas · 500 MW · withdrawn
- Onshore wind project GEN-2017-007, Curry CountyOnshore wind · 298 MW · withdrawn
- Solar project GEN-2020-062, Curry CountySolar · 256 MW · withdrawn
- Solar + storage project IA-PNM-2025-08, Curry CountySolar + storage · 250 MW · withdrawn
- Onshore wind project GEN-2022-171, Curry CountyOnshore wind · 200 MW · withdrawn
- Battery storage project GEN-2022-233, Curry CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2022-232, Curry CountySolar · 200 MW · withdrawn
- Other project GEN-2001-020, Curry CountyOther · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem