ONSHORE WIND Β· SPPOnshore wind project GEN-2022-171, Curry County
Onshore wind project GEN-2022-171, Curry County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Curry County, New Mexico, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-171
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Pleasant Hill 230 kV Substation
- Location
- Curry County, New Mexico
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 26 February 2023
- Proposed online date
- December 2026
- Withdrawn
- March 2025
Location
Marker shows the centre of Curry County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in Curry County
- Solar project GEN-2024-079, Curry CountySolar Β· 250 MW Β· in study
- Solar project GEN-2024-080, Curry CountySolar Β· 250 MW Β· in study
- Onshore wind project GEN-2024-089, Curry CountyOnshore wind Β· 195 MW Β· in study
- Gas project GEN-2001-005, Curry CountyGas Β· 640 MW Β· withdrawn
- Solar + storage project IA-PNM-2022-08, Curry CountySolar + storage Β· 500 MW Β· withdrawn
- Gas project GEN-2001-004, Curry CountyGas Β· 500 MW Β· withdrawn
- Onshore wind project GEN-2017-007, Curry CountyOnshore wind Β· 298 MW Β· withdrawn
- Solar project GEN-2020-062, Curry CountySolar Β· 256 MW Β· withdrawn
- Solar + storage project IA-PNM-2025-08, Curry CountySolar + storage Β· 250 MW Β· withdrawn
- Battery storage project GEN-2022-233, Curry CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project GEN-2022-232, Curry CountySolar Β· 200 MW Β· withdrawn
- Other project GEN-2001-020, Curry CountyOther Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem