Interconnection queue in PJM (Mid-Atlantic, Midwest) (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown444,774 MW
Active in queue4,774 MW44 requests
Agreement signed3,742 MW30 requests
Withdrawn23618.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Firelands Wind
Onshore wind
298 MWAgreement signed Erie, OHPJM Mar 2017target 2027
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Kingwood Solar
Solar
175 MWAgreement signed Greene, OHPJM Sep 2017target 2026
Spring Grove Solar II
Solar
150 MWAgreement signed Surry, VAPJM Jun 2017target 2025
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Riverstart Solar Park IV
Solar
150 MWAgreement signed Randolph, INPJM Sep 2017target 2025
Red Brick Solar
Solar
130 MWAgreement signed Lunenburg, VAPJM Dec 2017target 2026
Macadamia Solar
Solar
109 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Three Rivers Energy Center
Gas
103 MWAgreement signed Grundy, ILPJM Jul 20172023
Marion County Solar Project
Solar
100 MWAgreement signed Marion, OHPJM Apr 2017target 2025
Southwest Michigan Energy Center
Solar
100 MWAgreement signed Van Buren, MIPJM Dec 2017target 2027
Cartersville Solar
Solar
99.9 MWPaused / redesign Powhatan, VAPJM Mar 2017target 2026
Firefly Solar
Solar
96.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Firefly Solar
Solar
95.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Windsor PVI
Solar
85.0 MWPaused / redesign Isle Of Wight, VAPJM Mar 2017target 2023
Seven Bridges Solar
Solar
80.0 MWPaused / redesign Mecklenburg, VAPJM Sep 2017target 2026
Short Mountain Wind Energy
Onshore wind
80.0 MWPaused / redesign Hardy, WVPJM Sep 2017target 2024
Angelina Solar I
Solar
80.0 MWAgreement signed Preble, OHPJM Mar 2017target 2027
Sumac Solar
Solar
80.0 MWAgreement signed Bertie, NCPJM Jun 2017target 2028
Macadamia Solar
Solar
75.0 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Sweet Sue Solar
Solar
74.0 MWAgreement signed King William, VAPJM Sep 2017target 2026
Circleville Solar Energy
Solar
70.0 MWPaused / redesign Pickaway, OHPJM Feb 2017target 2027
Sweetleaf Solar
Solar
60.0 MWPaused / redesign Halifax, NCPJM Aug 2017target 2027
Chestnut Solar
Solar
60.0 MWPaused / redesign Marion, OHPJM Sep 2017target 2026
Greenwood Solar
Solar
50.0 MWAgreement signed Culpeper, VAPJM Sep 2017target 2027
Staley Solar
Solar
50.0 MWAgreement signed Kankakee, ILPJM Mar 2017target 2027
Eaton OH Solar
Solar
49.9 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Steubenville Solar
Solar
49.5 MWPaused / redesign Jefferson, OHPJM Nov 2017target 2027
Porter Mill Solar
Solar
45.8 MWAgreement signed Wicomico, MDPJM Jan 2017target 2026
Rochelle Solar
Solar
40.0 MWAgreement signed Ogle, ILPJM Apr 2017target 2028
Sweetleaf Solar
Solar
33.0 MWPaused / redesign Halifax, NCPJM Aug 2017target 2027
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Eaton OH Solar
Solar
20.0 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Walnut Solar I
Solar
20.0 MWAgreement signed King And Queen, VAPJM Mar 2017target 2026
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Blue Creek Wind Farm
Solar
20.0 MWPaused / redesign Van Wert, OHPJM Feb 2017target 2024
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
East Hagerstown Solar
Solar
11.8 MWAgreement signed Washington, MDPJM Mar 2017target 2026
Raceway Solar
Solar
10.0 MWAgreement signed Kent, DEPJM Apr 2017target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)