SOLAR · PJM

Angelina Solar I

Angelina Solar I is a 80.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Preble County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AC2-111
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
College Corner 138kV
Location
Preble County, Ohio
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
16 March 2017
Proposed online date
April 2027

Location

Marker shows the centre of Preble County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Preble County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem