Queue requests in study in PJM (Mid-Atlantic, Midwest) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown607,820 MW
Active in queue19.2 GW183 requests
Agreement signed11.3 GW123 requests
Withdrawn40938.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

60 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Cvow 2, Oss 2 โ€šร„รฌ T2G07
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
836 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 1, Oss 1 - T1L11
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
833 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Cvow 3, Oss 3 โ€šร„รฌ T3G15
Offshore wind ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
820 MWIn study City Of Chesapeake, VAPJM Sep 2019target 2032
Chesterfield CT Units 1 and 2
Gas ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Steward Creek Solar
Solar ยท Steward Creek Solar, LLC
300 MWIn study Lee, ILPJM Dec 2019target 2023
Three Lakes Solar
Solar + storage ยท Three Lakes Solar LLC
300 MWIn study St. Joseph, MIPJM Sep 2019target 2022
Black Diamond Solar
Solar ยท Black Diamond Solar Power, LLC
299 MWIn study Christian, ILPJM Mar 2019target 2022
Vermilion Grove Wind
Onshore wind ยท Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
South Dixon Solar
Solar ยท Deriva Energy Solar, LLC
200 MWIn study Lee, ILPJM Sep 2019target 2022
Gipper Wind Farm
Onshore wind ยท Gipper Wind Farm, LLC
191 MWIn study Whiteside, ILPJM Sep 2019target 2022
Martin County Solar Project
Solar
190 MWPaused / redesign Martin, KYPJM Sep 2019target 2028
Erie East Energy
Battery storage
160 MWPaused / redesign Erie, PAPJM Mar 2019target 2026
Bowfin Solar
Solar + storage
150 MWPaused / redesign Huntington, INPJM Aug 2019target 2028
Bright Stalk Generating Facility
Onshore wind ยท Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2019target 2022
Plano Skies Energy Center
Solar ยท Plano Skies Energy Center, LLC
150 MWIn study Kendall, ILPJM Mar 2019target 2022
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Kensington Solar
Solar
145 MWPaused / redesign Columbiana, OHPJM Mar 2019target 2026
Shorebird Solar
Solar
117 MWPaused / redesign Crawford, PAPJM Mar 2019target 2025
Plano Skies Energy Center
Solar ยท Plano Skies Energy Center, LLC
100 MWIn study Kendall, ILPJM May 2019target 2022
Clermont County Solar Project
Solar
100 MWPaused / redesign Clermont, OHPJM Mar 2019target 2025
Nottingham Solar
Solar
100 MWPaused / redesign Harrison, OHPJM Mar 20192023
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
Yadkins Energy Center
Battery storage ยท Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Madison Solar 1
Solar ยท AEUG Madison Solar, LLC
100 MWIn study Madison, KYPJM Mar 2019target 2021
Bedington Energy Facility
Solar
100 MWPaused / redesign Frederick, MDPJM Apr 2019target 2025
Rocky Ford Solar Energy Center
Solar
90.0 MWPaused / redesign Henry, VAPJM Mar 2019target 2026
Granite Hill Solar
Solar
70.0 MWPaused / redesign Adams, PAPJM Mar 2019target 2026
Morrow County Solar II
Solar
64.0 MWPaused / redesign Morrow, OHPJM Sep 2019target 2026
Dover Solar Facility
Solar
55.0 MWPaused / redesign Whitley, INPJM Mar 2019target 2026
Hardin Energy Center โ€šร„รฌ Storage II
Battery storage
55.0 MWPaused / redesign Hardin, OHPJM Mar 2019target 2026
Dover Solar
Solar
55.0 MWPaused / redesign York, PAPJM Mar 2019target 2026
Clermont County Solar Project
Battery storage
52.2 MWPaused / redesign Clermont, OHPJM Jun 2019target 2025
Maple Hill-Fiddlers 1 SP (Bear Rock)
Solar ยท CPV Maple Hill Solar, LLC
50.0 MWIn study Cambria, PAPJM Dec 2019target 2021
Switchgrass Solar 1
Solar
49.0 MWPaused / redesign Accomack, VAPJM Mar 2019target 2025
Amelia Energy Facility
Solar ยท Amelia Energy Facility, LLC
41.0 MWIn study Amelia, VAPJM Sep 2019target 2022
Woodstock Solar
Solar
40.0 MWPaused / redesign Champaign, OHPJM Mar 2019target 2026
Golden Aster Solar Energy Center
Battery storage
40.0 MWPaused / redesign Grant, INPJM Mar 2019target 2026
Henry County Solar
Solar
40.0 MWPaused / redesign Henry, OHPJM Sep 2019target 2026
Cottontail Solar 7
Solar
35.0 MWPaused / redesign Columbia, PAPJM Sep 2019target 2028
Meadow Forge Solar Energy Center
Solar
33.0 MWPaused / redesign Delaware, INPJM Mar 2019target 2026
Concho Solar I
Solar
20.0 MWPaused / redesign Queen Anne's, MDPJM May 2019target 2024
Momentum Gratz
Battery storage
20.0 MWPaused / redesign Dauphin, PAPJM Jun 2019target 2024
Mountain Holly
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2027
HU-Pauls
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Mar 2019target 2027
Montour 1
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2025
Dover Solar
Solar
20.0 MWPaused / redesign York, PAPJM Jul 2019target 2026
HU-Logging
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Feb 2019target 2024
Charles County Solar I
Solar
20.0 MWPaused / redesign Charles, MDPJM Apr 2019target 2028
SunEast Hooversville Solar
Solar
20.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)