Completed queue projects in PJM (Mid-Atlantic, Midwest)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests Β· page 1 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Greensville Generating Facility
Gas
1,681 MWOperating Greensville, VAPJM Oct 20132018
Nuclear project N13, Beaver County
Nuclear
1,630 MWOperating Beaver, PAPJM Nov 20042005
Brunswick Combined Cycle Power Station
Gas
1,526 MWOperating Brunswick, VAPJM Jul 20112016
Jackson Generation
Gas
1,201 MWOperating Will, ILPJM Oct 20162022
Three Rivers Energy Center
Gas
1,160 MWOperating Grundy, ILPJM Oct 20152023
South Field Energy Power Plant
Gas
1,152 MWOperating Columbiana, OHPJM Oct 20142021
Guernsey Power Station
Gas
1,100 MWOperating Guernsey, OHPJM Mar 20162023
Freedom Generation Plant
Gas
1,050 MWOperating Luzerne, PAPJM Mar 20142018
CPV Fairview Energy Center
Gas
1,050 MWOperating Cambria, PAPJM Oct 20142019
Gas project T94, Van Buren County
Gas
1,035 MWOperating Van Buren, MIPJM Oct 20072016
Lackawanna Thermal Generating Station
Gas
1,000 MWOperating Lackawanna, PAPJM Jan 20122018
Hickory Run Energy Station
Gas
1,000 MWOperating Lawrence, PAPJM Aug 20142019
Indeck Niles Energy Center
Gas
994 MWOperating Cass, MIPJM Apr 20152021
Warren County
Gas
950 MWOperating Warren, VAPJM Jul 20092014
Smithton Generating Station
Gas
930 MWOperating Westmoreland, PAPJM Jan 20082018
Patriot Generating Station
Gas
850 MWOperating Lycoming, PAPJM May 20112016
Liberty/Asylum Township Plant
Gas
850 MWOperating Bradford, PAPJM Apr 20112016
Wildcat Point
Gas
834 MWOperating Cecil, MDPJM Apr 20122017
Hunterstown
Gas
830 MWOperating Adams, PAPJM Jan 19992003
Stonewall Energy Park
Gas
800 MWOperating Loudoun, VAPJM Jan 20122017
Lordstown Energy Center
Gas
800 MWOperating Trumbull, OHPJM Feb 20142018
Oregon Energy Center
Gas
799 MWOperating Lucas, OHPJM Apr 20122017
Red Oak CC1, CT1 - CT4
Gas
765 MWOperating Middlesex, NJPJM Jan 19982002
Delta York
Gas
760 MWOperating York, PAPJM Feb 20132018
Bethlehem
Gas
750 MWOperating Northampton, PAPJM Apr 19992003
Linden 1, 2 & 3
Gas
750 MWOperating Union, NJPJM Apr 19972006
Carroll County Energy LLC
Gas
742 MWOperating Carroll, OHPJM Aug 20122017
Keys Energy Center
Gas
736 MWOperating Prince George's, MDPJM Jan 20122018
Woodbridge Energy Center
Gas
725 MWOperating Middlesex, NJPJM Nov 20102015
St. Charles Combined Cycle Facility
Gas
725 MWOperating Charles, MDPJM Aug 20092016
Phillips Island
Gas
725 MWOperating Philadelphia, PAPJM Aug 19982004
Ironwood
Gas
720 MWOperating Lebanon, PAPJM Apr 19972002
St. Joseph Energy Center, LLC
Gas
675 MWOperating St. Joseph, INPJM Jun 20112018
Bremo
Gas
675 MWOperating Buckingham, VAPJM Dec 20052011
West Deptford Energy Station
Gas
650 MWOperating Gloucester, NJPJM Jul 20062014
Newark Energy Center
Gas
625 MWOperating Essex, NJPJM Nov 20072015
Ronco CT1, CT2, STG
Gas
620 MWOperating Fayette, PAPJM Nov 20002003
Ford Mill
Gas
605 MWOperating Bucks, PAPJM Nov 19992004
South Bend CT1 - CT4
Gas
600 MWOperating Armstrong, PAPJM Jan 19992002
Lower Mt Bethel
Gas
600 MWOperating Northampton, PAPJM Aug 19972004
Nelson Energy Center
Gas
600 MWOperating ILPJM Oct 20062015
Longview ST1
Coal
600 MWOperating Monongalia, WVPJM May 20012008
Shawville Generating Station
Gas
590 MWOperating Clearfield, PAPJM Oct 20152016
Zion Energy Center
Gas
585 MWOperating Lake, ILPJM Jun 20072011
Dresden
Gas
580 MWOperating Muskingum, OHPJM Jul 20072011
Fox Squirrel Solar
Solar
577 MWOperating Madison, OHPJM Feb 20192024
Sewaren 7
Gas
568 MWOperating Middlesex, NJPJM Apr 20142018
Gas project A18, Berks County
Gas
557 MWOperating Berks, PAPJM May 19982002
Guernsey Power Station
Gas
550 MWOperating Guernsey, OHPJM Aug 20162022
Delta
Gas
550 MWOperating York, PAPJM Sep 20052011
Page 1 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)