πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

GAS Β· PJM

Wildcat Point

Wildcat Point is a 834 MW gas request built and operating in the PJM interconnection queue, in Cecil County, Maryland, connecting to Essential Power.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-065
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Essential Power
Connection point (POI)
Rock Springs 500kV
Location
Cecil County, Maryland
Technology
Gas: 834 MW
Total requested
834 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
27 April 2012
Proposed online date
September 2017
Came online
July 2017

Location

Marker shows the centre of Cecil County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Cecil County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem