Wildcat Point

Wildcat Point is a 166 MW gas request built and operating in the PJM interconnection queue, in Cecil County, Maryland, connecting to Essential Power.

Queue statusOperating
  1. PlanningQueued Apr 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-102
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Essential Power
Connection point (POI)
Rock Springs 500kV
Location
Cecil County, Maryland
Technology
Gas: 166 MW
Total requested
166 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 April 2013
Proposed online date
August 2017
Came online
July 2017

Location

Marker shows the centre of Cecil County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Cecil County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem