🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Maryland

GAS · PJM

Rock Springs Units 3 & 4

Rock Springs Units 3 & 4 is a 20.0 MW gas request built and operating in the PJM interconnection queue, in Cecil County, Maryland, connecting to ODEC.

Queue statusOperating
  1. PlanningQueued Oct 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
R20
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ODEC
Connection point (POI)
Rock Springs
Location
Cecil County, Maryland
Technology
Gas: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
4 October 2006
Proposed online date
July 2010
Came online
January 2007

Location

Marker shows the centre of Cecil County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Cecil County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem