GAS Β· PJM

Rocks Springs 1 & 2

Rocks Springs 1 & 2 is a 8.7 MW gas request built and operating in the PJM interconnection queue, in Cecil County, Maryland, connecting to ODEC.

Queue statusOperating
  1. PlanningQueued Nov 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
U4-015
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ODEC
Connection point (POI)
Rock Springs 500kV
Location
Cecil County, Maryland
Technology
Gas: 8.7 MW
Total requested
8.7 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
25 November 2008
Proposed online date
May 2009
Came online
May 2009

Location

Marker shows the centre of Cecil County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Cecil County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem