🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

GAS · PJM

West Deptford Energy Station

West Deptford Energy Station is a 650 MW gas request built and operating in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Jul 2006 (completed)
  2. ConsentedJun 2011 (completed)
  3. Construction (completed)
  4. OperatingAug 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q90
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Mickleton 230kV
Location
Gloucester County, New Jersey
Technology
Gas: 650 MW
Total requested
650 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
31 July 2006
Agreement signed
11 June 2011
Proposed online date
June 2016
Came online
August 2014

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem