Gas project T59, Gloucester County

Gas project T59, Gloucester County is a 14.4 MW gas request built and operating in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Sep 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
T59
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Mickleton
Location
Gloucester County, New Jersey
Technology
Gas: 14.4 MW
Total requested
14.4 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
21 September 2007
Proposed online date
July 2011
Came online
July 2011

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem