🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Monroe-Sicklerville Road LF Solar

Monroe-Sicklerville Road LF Solar is a 1.6 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AD2-135
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Williamstown 12kV
Location
Gloucester County, New Jersey
Technology
Solar: 1.6 MW
Total requested
1.6 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
23 March 2018
Proposed online date
March 2025

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem