Paradise SP

Paradise SP is a 5.1 MW solar request built and operating in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jan 2009 (completed)
  2. ConsentedJan 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
U4-036
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Gloucester 26.4kV
Location
Gloucester County, New Jersey
Technology
Solar: 5.1 MW
Total requested
5.1 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
28 January 2009
Agreement signed
29 January 2010
Proposed online date
January 2011
Came online
December 2009

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem