United States › Grid › Interconnection queues › Pennsylvania

GAS · PJM

CPV Fairview Energy Center

CPV Fairview Energy Center is a 1,050 MW gas request built and operating in the PJM interconnection queue, in Cambria County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Oct 2014 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AA1-076
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Hunterstown-Conemaugh 500kV
Location
Cambria County, Pennsylvania
Technology
Gas: 1,050 MW
Total requested
1,050 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
22 October 2014
Proposed online date
March 2021
Came online
September 2019

Location

Marker shows the centre of Cambria County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Cambria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem