United States › Grid › Interconnection queues › Pennsylvania
GAS · PJMLower Mt Bethel
Lower Mt Bethel is a 600 MW gas request built and operating in the PJM interconnection queue, in Northampton County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- A12
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Martins Creek 230 kV
- Location
- Northampton County, Pennsylvania
- Technology
- Gas: 600 MW
- Total requested
- 600 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 20 August 1997
- Proposed online date
- May 2004
- Came online
- May 2004
Location
Marker shows the centre of Northampton County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Northampton County
- Solar + storage project AI1-152, Northampton CountySolar + storage · 19.9 MW · in study
- BethlehemGas · 750 MW · built
- Conectiv Bethlem CT 6, ST2Gas · 350 MW · built
- Lower Mount BethelGas · 86.6 MW · built
- Bethlehem Gen Facility Units 1 - 8Gas · 42.0 MW · built
- Lower Mount BethelGas · 33.0 MW · built
- Martins Creek #3Coal · 30.0 MW · built
- Martins Creek #4Coal · 30.0 MW · built
- Grand Central Sanitary LFOther · 10.0 MW · built
- Portland Station Unit 5Gas · 6.5 MW · built
- Bethlehem LFOther · 5.0 MW · built
- Bethlehem LandfillOther · 5.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem