United States › Grid › Interconnection queues › Ohio
GAS · PJMLordstown Energy Center
Lordstown Energy Center is a 800 MW gas request built and operating in the PJM interconnection queue, in Trumbull County, Ohio, connecting to ATSI.
Request details
- Queue ID
- Z2-028
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Highland-Sammis 345kV & Highland-Mansfield 345kV
- Location
- Trumbull County, Ohio
- Technology
- Gas: 800 MW
- Total requested
- 800 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 21 February 2014
- Proposed online date
- December 2018
- Came online
- August 2018
Location
Marker shows the centre of Trumbull County; the queue data does not give exact sites.
Other requests in Trumbull County
- Trumbull Energy CenterGas · 940 MW · agreement signed
- Gas project AJ1-023, Trumbull CountyGas · 70.0 MW · in study
- Solar + storage project AH2-239, Trumbull CountySolar + storage · 49.0 MW · in study
- Gas project AH1-706, Trumbull CountyGas · 30.5 MW · in study
- Lordstown Energy CenterGas · 140 MW · built
- Warren Natural Gas Generation FaciilityGas · 16.5 MW · built
- Niles A CTOther · 1.5 MW · built
- Gas project AE1-213, Trumbull CountyGas · 1,170 MW · withdrawn
- Gas project AE2-013, Trumbull CountyGas · 1,170 MW · withdrawn
- Gas project AD2-057, Trumbull CountyGas · 940 MW · withdrawn
- Gas project Z1-034, Trumbull CountyGas · 217 MW · withdrawn
- Onshore wind project H091, Trumbull CountyOnshore wind · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem