Lordstown Energy Center

Lordstown Energy Center is a 140 MW gas request built and operating in the PJM interconnection queue, in Trumbull County, Ohio, connecting to ATSI.

Queue statusOperating
  1. PlanningQueued Jun 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB1-017
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Highland-Sammis 345 kV & Highland-Mansfield 345 kV
Location
Trumbull County, Ohio
Technology
Gas: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
18 June 2015
Proposed online date
December 2018
Came online
August 2018

Location

Marker shows the centre of Trumbull County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Trumbull County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem