ONSHORE WIND Β· MISOOnshore wind project H091, Trumbull County
Onshore wind project H091, Trumbull County is a 101 MW onshore wind request withdrawn in the MISO interconnection queue, in Trumbull County, Ohio.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2008 (completed)
- Withdrawn / abandonedNov 2008 (project stopped here)
- ConsentedNov 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H091
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Ohio Edison 138kV Cortland Substation
- Location
- Trumbull County, Ohio
- Technology
- Wind: 101 MW
- Total requested
- 101 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 24 July 2008
- Agreement signed
- 7 November 2008
- Proposed online date
- July 2011
- Withdrawn
- November 2008
Location
Marker shows the centre of Trumbull County; the queue data does not give exact sites.
Other requests in Trumbull County
- Trumbull Energy CenterGas Β· 940 MW Β· agreement signed
- Gas project AJ1-023, Trumbull CountyGas Β· 70.0 MW Β· in study
- Solar + storage project AH2-239, Trumbull CountySolar + storage Β· 49.0 MW Β· in study
- Gas project AH1-706, Trumbull CountyGas Β· 30.5 MW Β· in study
- Lordstown Energy CenterGas Β· 800 MW Β· built
- Lordstown Energy CenterGas Β· 140 MW Β· built
- Warren Natural Gas Generation FaciilityGas Β· 16.5 MW Β· built
- Niles A CTOther Β· 1.5 MW Β· built
- Gas project AE1-213, Trumbull CountyGas Β· 1,170 MW Β· withdrawn
- Gas project AE2-013, Trumbull CountyGas Β· 1,170 MW Β· withdrawn
- Gas project AD2-057, Trumbull CountyGas Β· 940 MW Β· withdrawn
- Gas project Z1-034, Trumbull CountyGas Β· 217 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem