United States โบ Grid โบ Interconnection queues โบ Illinois
OCTARY USA ยท INTERCONNECTION QUEUESInterconnection queue in Illinois, PJM
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Heritage Prairie Wind Onshore wind |
850 MW | Agreement signed |
| Battery storage project AH2-416, Livingston County Battery storage |
450 MW | In study |
| Battery storage project AG2-545, Mchenry County Battery storage ยท Monarch Grid, LLC |
400 MW | In study |
| Battery storage project AJ1-012, Lake County Battery storage |
354 MW | In study |
| Solar project AH2-340, Stark County Solar |
350 MW | In study |
| Panther Grove Wind Onshore wind |
350 MW | Agreement signed |
| Battery storage project AJ1-011, Lake County Battery storage |
328 MW | In study |
| Pleasant Grove Solar Solar ยท Deriva Energy Solar, LLC |
300 MW | In study |
| Onshore wind project AH2-270, Whiteside County Onshore wind |
300 MW | In study |
| Battery storage project AI1-024, Mclean County Battery storage |
300 MW | In study |
| Steward Creek Solar Solar ยท Steward Creek Solar, LLC |
300 MW | In study |
| Panther Grove 2 Onshore wind |
300 MW | Agreement signed |
| Dawson Solar Solar ยท Deriva Energy Solar, LLC |
300 MW | In study |
| Battery storage project AH2-415, Livingston County Battery storage |
300 MW | In study |
| Burr Oak Solar Solar ยท Leeward Renewable Energy Development, LLC |
300 MW | In study |
| South Dixon Solar Solar ยท Deriva Energy Solar, LLC |
300 MW | In study |
| Solar project AG2-363, Tazewell County Solar ยท Mackinaw Solar LLC |
300 MW | In study |
| Black Diamond Solar Solar ยท Black Diamond Solar Power, LLC |
299 MW | In study |
| Solar project AG2-453, Kendall County Solar ยท Fox Valley Energy Facility, LLC |
280 MW | In study |
| Solar project AH2-342, Stark County Solar |
280 MW | In study |
| Beacon Solar Solar ยท Beacon Solar, LLC |
260 MW | In study |
| Battery storage project AJ1-014, Will County Battery storage |
260 MW | In study |
| Livingston Wind Onshore wind ยท Livingston Wind Project, LLC |
255 MW | In study |
| Gipper Solar Farm Solar ยท Gipper Solar Farm, LLC |
255 MW | In study |
| Battery storage project AI1-149, Mchenry County Battery storage |
250 MW | In study |
| Battery storage project AJ1-013, Will County Battery storage |
250 MW | In study |
| Solar + storage project AI1-172, Grundy County Solar + storage |
250 MW | In study |
| Solar + storage project AH2-113, Livingston County Solar + storage |
250 MW | In study |
| Battery storage project AI1-154, Will County Battery storage |
230 MW | In study |
| Battery storage project AH2-421, Grundy County Battery storage |
230 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
210 MW | Paused / redesign |
| Solar + storage project AH2-363, Kankakee County Solar + storage |
200 MW | In study |
| Solar project AH1-151, Lee County Solar ยท Steward Creek Solar, LLC |
200 MW | In study |
| Solar project AH1-150, Lee County Solar ยท Steward Creek Solar, LLC |
200 MW | In study |
| Steward Creek Solar Solar ยท Steward Creek Solar, LLC |
200 MW | In study |
| South Dixon Solar Solar ยท Deriva Energy Solar, LLC |
200 MW | In study |
| Onshore wind project AI1-191, Stephenson County Onshore wind |
200 MW | In study |
| Blooming Grove Solar Energy Center Solar |
200 MW | Agreement signed |
| Solar project AG2-364, Tazewell County Solar ยท Mackinaw Solar LLC |
200 MW | In study |
| Rolling Farms Wind Project Onshore wind |
200 MW | Agreement signed |
| Riverbank Energy Battery storage ยท Lincoln Reserve Energy, LLC |
200 MW | In study |
| Battery storage project AI1-023, Mclean County Battery storage |
200 MW | In study |
| Battery storage project AG2-544, Mchenry County Battery storage ยท Monarch Grid, LLC |
200 MW | In study |
| Solar project AH1-044, Lee County Solar ยท Steward Creek Solar, LLC |
200 MW | In study |
| Lower Crossing Wind Onshore wind |
200 MW | Paused / redesign |
| Gipper Wind Farm Onshore wind ยท Gipper Wind Farm, LLC |
191 MW | In study |
| Solar project AH1-338, Lee County Solar ยท Prairie Brome Solar LLC |
180 MW | In study |
| Nuclear project AH1-714, Lasalle County Nuclear ยท Constellation Energy Generation, LLC |
174 MW | In study |
| Solar + storage project AH2-258, Kendall County Solar + storage |
172 MW | In study |
| Battery storage project AH2-259, Kendall County Battery storage |
172 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)