Other project J1656, Vermilion County Other |
412 MW | Withdrawn / abandoned |
Vermilion, IL | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1613, Cass County Onshore wind |
400 MW | Withdrawn / abandoned |
Cass, ND | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1621, Mcpherson County Onshore wind |
400 MW | Withdrawn / abandoned |
Mcpherson, SD | MISO |
Jun 2020 | target 2023 |
Gas project J1838, Dane County Gas |
320 MW | Withdrawn / abandoned |
Dane, WI | MISO |
Jun 2020 | target 2025 |
Solar + storage project J1756, Shelby County Solar + storage |
309 MW | Withdrawn / abandoned |
Shelby, IN | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1757, Coles County Onshore wind |
300 MW | Withdrawn / abandoned |
Coles, IL | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1666, Ingham County Onshore wind |
300 MW | Withdrawn / abandoned |
Ingham, MI | MISO |
Jun 2020 | target 2023 |
Solar project J1753, Green County Solar |
300 MW | Withdrawn / abandoned |
Green, WI | MISO |
Jun 2020 | target 2024 |
Onshore wind project J1676, Mclean County Onshore wind |
300 MW | Withdrawn / abandoned |
Mclean, IL | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1702, Shelby County Onshore wind |
300 MW | Withdrawn / abandoned |
Shelby, IL | MISO |
Jun 2020 | target 2023 |
Solar project J1682, Boone County Solar |
300 MW | Withdrawn / abandoned |
Boone, IN | MISO |
Jun 2020 | target 2024 |
Onshore wind project J1812, Chambers County Onshore wind |
294 MW | Withdrawn / abandoned |
Chambers, TX | MISO |
Jun 2020 | target 2024 |
Solar project J1742, Porter County Solar |
294 MW | Withdrawn / abandoned |
Porter, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1700, Johnson County Solar |
288 MW | Withdrawn / abandoned |
Johnson, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1741, Cass County Solar |
270 MW | Withdrawn / abandoned |
Cass, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1538, Livingston Parish County Solar |
268 MW | Withdrawn / abandoned |
Livingston Parish, LA | MISO |
Jun 2020 | target 2023 |
Solar + storage project J1685, Ascension Parish County Solar + storage |
250 MW | Withdrawn / abandoned |
Ascension Parish, LA | MISO |
Jun 2020 | target 2023 |
Solar + storage project J1674, St. Tammany Parish County Solar + storage |
250 MW | Withdrawn / abandoned |
St. Tammany Parish, LA | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1675, Edgar County Onshore wind |
250 MW | Withdrawn / abandoned |
Edgar, IL | MISO |
Jun 2020 | target 2023 |
Solar project J1547, Franklin County Solar |
250 MW | Withdrawn / abandoned |
Franklin, IA | MISO |
Jun 2020 | target 2023 |
Solar project J1623, Orange County Solar |
200 MW | Withdrawn / abandoned |
Orange, IN | MISO |
Jun 2020 | target 2024 |
Solar project J1579, Edwards County Solar |
200 MW | Withdrawn / abandoned |
Edwards, IL | MISO |
Jun 2020 | target 2023 |
Solar project J1531, Sherburne County Solar |
200 MW | Withdrawn / abandoned |
Sherburne, MN | MISO |
Jun 2020 | target 2023 |
Solar project J1543, Grand Traverse County Solar |
200 MW | Withdrawn / abandoned |
Grand Traverse, MI | MISO |
Jun 2020 | target 2023 |
Solar project J1592, Pope County Solar |
200 MW | Withdrawn / abandoned |
Pope, AR | MISO |
Jun 2020 | target 2023 |
Solar project J1688, Champaign County Solar |
200 MW | Withdrawn / abandoned |
Champaign, IL | MISO |
Jun 2020 | target 2023 |
Surplus; J913 Other |
200 MW | Withdrawn / abandoned |
White, IN | MISO |
Nov 2020 | |
Solar project J1578, Bartholomew County Solar |
200 MW | Withdrawn / abandoned |
Bartholomew, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1526, St. Clair County Solar |
200 MW | Withdrawn / abandoned |
St. Clair, MI | MISO |
Jun 2020 | target 2026 |
Solar project J1705, Columbia County Solar |
200 MW | Withdrawn / abandoned |
Columbia, WI | MISO |
Jun 2020 | target 2024 |
Solar project J1563, Putnam County Solar |
200 MW | Withdrawn / abandoned |
Putnam, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1540, Cass County Solar |
200 MW | Withdrawn / abandoned |
Cass, ND | MISO |
Jun 2020 | target 2024 |
Onshore wind project J1594, Clark County Onshore wind |
200 MW | Withdrawn / abandoned |
Clark, SD | MISO |
Jun 2020 | target 2023 |
Solar project J1515, Midland County Solar |
200 MW | Withdrawn / abandoned |
Midland, MI | MISO |
Jun 2020 | target 2023 |
Solar project J1661, Lapeer County Solar |
200 MW | Withdrawn / abandoned |
Lapeer, MI | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1628, White County Onshore wind |
200 MW | Withdrawn / abandoned |
White, IN | MISO |
Jun 2020 | target 2022 |
Solar project J1697, Lawrence County Solar |
200 MW | Withdrawn / abandoned |
Lawrence, IN | MISO |
Jun 2020 | target 2023 |
Solar project J1541, Calcasieu Parish County Solar |
200 MW | Withdrawn / abandoned |
Calcasieu Parish, LA | MISO |
Jun 2020 | target 2023 |
Solar project J1681, Maries County Solar |
200 MW | Withdrawn / abandoned |
Maries, MO | MISO |
Jun 2020 | target 2024 |
Onshore wind project J1667, Isabella County Onshore wind |
200 MW | Withdrawn / abandoned |
Isabella, MI | MISO |
Jun 2020 | target 2023 |
Solar project J1632, Caldwell County Solar |
200 MW | Withdrawn / abandoned |
Caldwell, KY | MISO |
Jun 2020 | target 2023 |
Solar project J1544, Morton County Solar |
200 MW | Withdrawn / abandoned |
Morton, ND | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1754, Mchenry County Onshore wind |
200 MW | Withdrawn / abandoned |
Mchenry, ND | MISO |
Jun 2020 | target 2023 |
Solar project J1570, Rock County Solar |
200 MW | Withdrawn / abandoned |
Rock, MN | MISO |
Jun 2020 | target 2023 |
Solar project J1522, Muskegon County Solar |
200 MW | Withdrawn / abandoned |
Muskegon, MI | MISO |
Jun 2020 | target 2023 |
Solar project J1556, Ottawa County Solar |
200 MW | Withdrawn / abandoned |
Ottawa, MI | MISO |
Jun 2020 | target 2023 |
Onshore wind project J1822, Franklin County Onshore wind |
200 MW | Withdrawn / abandoned |
Franklin, IA | MISO |
Jun 2020 | target 2023 |
Battery storage project J1491, Marion County Battery storage |
200 MW | Withdrawn / abandoned |
Marion, IN | MISO |
Jun 2020 | target 2022 |
Solar project J1726, Pulaski County Solar |
200 MW | Withdrawn / abandoned |
Pulaski, IN | MISO |
Jun 2020 | target 2023 |
Solar + storage project J1830, Pulaski County Solar + storage |
200 MW | Withdrawn / abandoned |
Pulaski, IL | MISO |
Jun 2020 | target 2023 |