πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J1592, Pope County

Solar project J1592, Pope County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Pope County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1592
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
MORRILTON EAST - Atkins 161 kV
Location
Pope County, Arkansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
18 June 2020
Proposed online date
April 2023
Withdrawn
December 2023

Location

Marker shows the centre of Pope County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Pope County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem