Solar + storage project J1685, Ascension Parish County

Solar + storage project J1685, Ascension Parish County is a 250 MW solar + storage request withdrawn in the MISO interconnection queue, in Ascension Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedSep 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1685
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Donaldsonville to Evergreen 230kV line
Location
Ascension Parish County, Louisiana
Technology
Solar: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 June 2020
Proposed online date
September 2023
Withdrawn
September 2020

Location

Marker shows the centre of Ascension Parish County; the queue data does not give exact sites.