Withdrawn queue requests in Texas, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7015.9 GW
Active in queue6,659 MW27 requests
Agreement signed332 MW3 requests
Withdrawn7015.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

70 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J480, Cherokee County
Gas
1,240 MWWithdrawn / abandoned Cherokee, TXMISO Sep 2015
Gas project J487, San Jacinto County
Gas
999 MWWithdrawn / abandoned San Jacinto, TXMISO Oct 2015target 2020
Gas project J539, Newton County
Gas
999 MWWithdrawn / abandoned Newton, TXMISO Nov 2015target 2019
Gas project J3708, Jefferson County
Gas
770 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2027
Solar project J2168, Jefferson County
Solar
693 MWWithdrawn / abandoned Jefferson, TXMISO Aug 2021target 2024
Solar project J3441, Houston County
Solar
500 MWWithdrawn / abandoned Houston, TXMISO Mar 2024target 2028
Gas project J3605, Liberty County
Gas
465 MWWithdrawn / abandoned Liberty, TXMISO Apr 2024target 2027
Gas project J479, Grimes County
Gas
462 MWWithdrawn / abandoned Grimes, TXMISO Sep 2015target 2018
Solar project J3596, Harris County
Solar
460 MWWithdrawn / abandoned Harris, TXMISO Apr 2024target 2029
Solar + storage project J2953, Orange County
Solar + storage
400 MWWithdrawn / abandoned Orange, TXMISO Sep 2022target 2026
Solar project J3409, Newton County
Solar
400 MWWithdrawn / abandoned Newton, TXMISO Apr 2024target 2028
Gas project J369, Newton County
Gas
393 MWWithdrawn / abandoned Newton, TXMISO May 2014target 2017
Onshore wind project J2910, Chambers County
Onshore wind
303 MWWithdrawn / abandoned Chambers, TXMISO Sep 2022target 2026
Onshore wind project J3262, Jefferson County
Onshore wind
300 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2028
Onshore wind project J1812, Chambers County
Onshore wind
294 MWWithdrawn / abandoned Chambers, TXMISO Jun 2020target 2024
Battery storage project J3086, Peoria County
Battery storage
253 MWWithdrawn / abandoned Peoria, TXMISO Sep 2022target 2026
Battery storage project J4104, Houston County
Battery storage
250 MWWithdrawn / abandoned Houston, TXMISO Oct 2025target 2030
Solar project J3455, Trinity County
Solar
250 MWWithdrawn / abandoned Trinity, TXMISO Mar 2024target 2028
Solar project J3768, Walker County
Solar
250 MWWithdrawn / abandoned Walker, TXMISO Apr 2024target 2028
Solar project J2851, Walker County
Solar
250 MWWithdrawn / abandoned Walker, TXMISO Sep 2022target 2027
Solar + storage project J2076, San Jacinto County
Solar + storage
225 MWWithdrawn / abandoned San Jacinto, TXMISO Aug 2021target 2024
Battery storage project J3087, Logan County
Battery storage
205 MWWithdrawn / abandoned Logan, TXMISO Sep 2022target 2026
Solar + storage project J2041, Jefferson County
Solar + storage
200 MWWithdrawn / abandoned Jefferson, TXMISO Aug 2021target 2025
Solar project J867, Polk County
Solar
200 MWWithdrawn / abandoned Polk, TXMISO Jun 2017target 2019
Solar project J2767, Liberty County
Solar
200 MWWithdrawn / abandoned Liberty, TXMISO Sep 2022target 2026
Onshore wind project J3972, Liberty County
Onshore wind
200 MWWithdrawn / abandoned Liberty, TXMISO Mar 2025target 2029
Solar project J3079, Jasper County
Solar
200 MWWithdrawn / abandoned Jasper, TXMISO Sep 2022target 2026
Solar project J1100, Grimes County
Solar
200 MWWithdrawn / abandoned Grimes, TXMISO Mar 2018target 2021
Solar project J3194, Hardin County
Solar
198 MWWithdrawn / abandoned Hardin, TXMISO Sep 2022target 2025
Solar + storage project J3821, Walker County
Solar + storage
175 MWWithdrawn / abandoned Walker, TXMISO Apr 2024target 2028
Solar project J911, Montgomery County
Solar
150 MWWithdrawn / abandoned Montgomery, TXMISO Jun 2017target 2020
Battery storage project J3299, Jefferson County
Battery storage
150 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2027
Battery storage project J3123, Orange County
Battery storage
150 MWWithdrawn / abandoned Orange, TXMISO Sep 2022target 2026
Solar project J3610, Tyler County
Solar
150 MWWithdrawn / abandoned Tyler, TXMISO Apr 2024target 2028
Onshore wind project J1120, Jefferson County
Onshore wind
145 MWWithdrawn / abandoned Jefferson, TXMISO Mar 2018target 2021
Solar + storage project J2114, Tyler County
Solar + storage
140 MWWithdrawn / abandoned Tyler, TXMISO Dec 2021target 2024
Solar + storage project J2688, Newton County
Solar + storage
130 MWWithdrawn / abandoned Newton, TXMISO Sep 2022target 2026
Solar project J1277, Liberty County
Solar
130 MWWithdrawn / abandoned Liberty, TXMISO Apr 2019target 2022
Solar project J2817, Liberty County
Solar
120 MWWithdrawn / abandoned Liberty, TXMISO Sep 2022target 2024
Solar project J2683, Hardin County
Solar
120 MWWithdrawn / abandoned Hardin, TXMISO Sep 2022target 2026
Solar project J2112, Hardin County
Solar
115 MWWithdrawn / abandoned Hardin, TXMISO Dec 2021target 2024
Gas project J3587, Jefferson County
Gas
110 MWWithdrawn / abandoned Jefferson, TXMISO Apr 2024target 2027
Solar project J418, Polk County
Solar
100 MWWithdrawn / abandoned Polk, TXMISO Jun 2017target 2016
Solar project J502, Orange County
Solar
100 MWWithdrawn / abandoned Orange, TXMISO Jun 2017target 2019
Solar project J1186, San Jacinto County
Solar
100 MWWithdrawn / abandoned San Jacinto, TXMISO Mar 2018target 2020
Solar project J2243, Tyler County
Solar
100 MWWithdrawn / abandoned Tyler, TXMISO Aug 2021target 2024
Battery storage project J2235, San Jacinto County
Battery storage
100 MWWithdrawn / abandoned San Jacinto, TXMISO Aug 2021target 2022
Solar project J1279, Hardin County
Solar
100 MWWithdrawn / abandoned Hardin, TXMISO Apr 2019target 2022
Battery storage project J2253, Tyler County
Battery storage
100 MWWithdrawn / abandoned Tyler, TXMISO Aug 2021target 2022
Solar project J932, Liberty County
Solar
100 MWWithdrawn / abandoned Liberty, TXMISO Jun 2017target 2019
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)