Solar project J932, Liberty County

Solar project J932, Liberty County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Liberty County, Texas, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J932
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Porter - China 230 kV Line
Location
Liberty County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2019
Withdrawn
January 2019

Location

Marker shows the centre of Liberty County; the queue data does not give exact sites.