United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· MISOSolar project J502, Orange County
Solar project J502, Orange County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Orange County, Texas, connecting to Entergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J502
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- McLewis 230 kV Substation
- Location
- Orange County, Texas
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2019
- Withdrawn
- January 2019
Location
Marker shows the centre of Orange County; the queue data does not give exact sites.
Other requests in Orange County
- Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1Gas Β· 1,166 MW Β· in study
- Solar project J3045, Orange CountySolar Β· 300 MW Β· in study
- Gas project J1834, Orange CountyGas Β· 126 MW Β· in study
- Solar + storage project J2953, Orange CountySolar + storage Β· 400 MW Β· withdrawn
- Battery storage project J3123, Orange CountyBattery storage Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem