United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR + STORAGE Β· MISOSolar + storage project J3821, Walker County
Solar + storage project J3821, Walker County is a 175 MW solar + storage request withdrawn in the MISO interconnection queue, in Walker County, Texas, connecting to ENTERGY TEXAS, INC..
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3821
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY TEXAS, INC.
- Connection point (POI)
- RIVTRIN
- Location
- Walker County, Texas
- Technology
- Solar: 175 MW Β· Battery
- Total requested
- 175 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 18 April 2024
- Proposed online date
- August 2028
- Withdrawn
- December 2025
Location
Marker shows the centre of Walker County; the queue data does not give exact sites.
Other requests in Walker County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem