πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR + STORAGE Β· MISO

Solar + storage project J2041, Jefferson County

Solar + storage project J2041, Jefferson County is a 200 MW solar + storage request withdrawn in the MISO interconnection queue, in Jefferson County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2041
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Amelia North substation
Location
Jefferson County, Texas
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 August 2021
Proposed online date
September 2025
Withdrawn
March 2025

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem